Demolition and site clearing of existing site improvements + Bulk Excavation (circa 18,500 cubic metres), installation of a site retention system (piling, anchoring and shotcrete wall perimeter) + environmental controls throughout duration of the Project.
Demolition and site clearing of existing site improvements + Bulk Excavation (circa 18,500 cubic metres), installation of a site retention system (piling, anchoring and shotcrete wall perimeter) + environmental controls throughout duration of the Project.